Sunday, September 15, 2019

BURYING BAD NEWS


If the Welsh Labour Government in Cymru / Wales was looking for a good day to bury bad news for the people of Newport then perhaps Wednesday 28th August was probably a good day. 

I mention this because back in April 2017, a list of 12 potential new and revived railway station sites was made public which would go a long way towards adding connectively to various parts of our country’s poor railway network and potentially reducing road congestion. 

On the 28th August 2019, it was revealed that the original list of 12 has now become  4  - when another list of 4 was published. Now this is not a definitive list, and there are no guarantees that  these 4 prospective railway stations will eventually be built or re-opened as they have to go on for yet further assessment in Westminster. 

The lucky 4 prospective railway stations are: 

  • Ely Mill/Victoria Park in Cardiff
  • St Clears in Carmarthenshire
  • Deeside Industrial Park/Northern Gateway
  • Carno in Powys

The railway stations which did not made it through the assessment are:

  • Llanwern
  • Newport Road/Rover Way
  • St Mellons
  • Cockett
  • Landore
  • North Wrexham
  • South Wrexham
  • Llangefni

It is important to remember that control of our railway infrastructure investment is not devolved to Cymru / Wales - a decision largely made by the then Labour Government in Westminster.  it still remains with the UK Westminster Government, all the Welsh Labour Government does is draw up a short list of suggestions.

All potential stations go through three stages of assessment.

  • The first looks at Welsh Transport Appraisal Guidance criteria and consideration of the Wellbeing and Future Generations Act.
  • The second looks at the strength of the financial and economic case for a new station and advice from Network Rail on deliverability.

  • The third is "development and assessment of the highest priorities".

To help narrow the list down, station demand forecasts were drawn up which are designed to give a likely viability of proposed stations. This may actually sound a more scientific and rational process than it is. It is worth remembering that the anticipated number of passengers who were expected to travel on the reopened Ebbw Vale line to Cardiff in 12 months travelled on the new service in the first 4 months. 

A word of warning - please don’t hold your breath in anticipation of any regular train service from Ebbw Vale to Newport - we may yet have along wait. The 7,000 + householders who will end up living on the Llanwern site will have no option but to use their cars or the bus service to get to and from work. Not pushing for a railway station at Llanwern will directly impact on the congestion in an around Newport, on the SDR and the existing M4. 

Any proposal will only be successful with "a sound business case" and the assessment "increases the ability of station proposals to be in a position to benefit from funding calls" - and that decision will be made in Westminster rather than here in Cymru / Wales. A Welsh Government spokesman said: "The stations that scored the highest in the assessment will now be taken forward. The proposals for the remaining stations will be considered when additional resources become available."

It is also worth noting that the process is ongoing and there is no date for any potential reopening of any station. Considering that for the last 3 years Westminster has been tearing itself apart over BREXIT it would be a safe bet that it may be a while before any Westminster government focuses on Cymru / Wales and our national interests. Decisions about railway infrastructure development need to be made here in Cymru / Wales, not in Westminster.

Thursday, January 3, 2019

REAL ALTERNATIVES


One of the reasons why we have little choice but to use our cars and the M4 to get around Newport (and to go to work) is because of the lack of any reasonable alternative easily accessible means of public transport. By now even the Welsh Labour government has finally run out of tired excuses and soft weasel words to hide their inaction and failure to deliver much beyond sound bites and logo laden graphic images. 

Occasionally seen but rarely advertised...
The simple but abject failure to connect the Ebbw Vale line to Newport means that commuters living in communities in the Ebbw Valley still remain unable to travel directly to Newport (and beyond) by train and have a real choice but to use their cars. They are denied the opportunity of catching connecting trains to Newport, Bristol, London, Cheltenham and beyond as well as possibly travelling slightly more rapidly to Cardiff in the morning and evening as result of the failure to run a fast service direct from Abertillery to Cardiff as originally promised. 

This leaves commuters no choice but to drive to work and help to feed the congestion of an already at times overcrowded M4. The Ebbw Vale line, at least to Cardiff, which reopened in 2008 and carried  a years worth of anticipated passengers in the first few months, made a real difference. It's a fact that the new rail service failed to connect to Newport from day one - despite the implied promises and suggestions made before and since the railway line was reopened. 

Ironically to all intents and purposes is already open – trains already run by stealth on occasions from Ebbw Vale into Newport and vice versa. The rail line and the signalling works fine – what we need is a regularly timetabled rail service - preferably now rather than later. Long overdue decisions about our infrastructure could make a real and significant difference and begin the process of providing realistic alternatives to everyday car use. 

Construction of railway stations at Caerleon / Ponthir, Llanwern and Magor - with well planned walk routes, safe, secure park and ride. Any railway stations should also include decent facilities which would make a real difference - along with the reinstatement of a more functional bus service (that's connected to the new railway stations). Elsewhere in Europe where significant housing developments are planned the infrastructure - often railway stations, tram stops and transport hubs are constructed first before any houses are built - but just not here.

By now the Welsh Labour government (even with new leadership) has run out of old excuses and soft weasel words to hide their failure to deliver. Our transport and infrastructure problems require political solutions and political decisions - something that will not come from the current incumbent inert Labour government in Cardiff Bay. With a post BREXIT world rapidly approaching- some hard sensible sustainable longer term choices need to be made with a degree of urgency - one of those should be to start work on (those parts of) the Metro that will make a real difference.